DATE: April 8, 2010

UNOFFICIAL BID RESULTS
OFFICIAL RESULTS TO BE DETERMINED BY
THE NEBRASKA DEPARTMENT OF ROADS
CALL ORDER: 100
PROJECT NO.: NH-77-1(119)
Gage County
Return to Lettings Index Page
|
CONTRACTOR |
TOTAL |
| CONSTRUCTORS
INC |
4,832,222 |
|
DOBSON BROTHERS CONST CO & AFFIL |
5,886,443 |
|
HALL BROTHERS RECYCLING & RECLAM |
5,487,769 |
| KNIFE
RIVER MIDWEST LLC |
|
| PAVERS
COMPANIES |
|
| U S
ASPHALT CO |
5,542,536 |
| VONTZ
PAVING INC |
|
| WERNER
CONSTRUCTION INC |
5,252,278 |
| WESTERN
ENGINEERING CO INC |
|
| |
|

CALL ORDER: 200
PROJECT NO.: RD-31-2(1010)
Sarpy County
Return to Lettings Index Page
|
CONTRACTOR |
TOTAL |
| CONSTRUCTORS
INC |
1,399,996 |
|
DOBSON BROTHERS CONST CO & AFFIL |
1,519,365 |
|
OMNI ENGINEERING INC & SUBSID |
1,490,702 |
| PAVERS |
1,519,889 |
| WERNER
CONSTRUCTION INC |
|
| WESTERN
ENGINEERING CO INC |
1,687,516 |
| |
|
| |
|

CALL ORDER: 300
PROJECT NO.: RD-12-5(1012)
Knox County
Return to Lettings Index Page
|
CONTRACTOR |
TOTAL |
| KNIFE
RIVER MIDWEST LLC |
3,157,465 |
|
WERNER CONSTRUCTION INC |
3,131,028 |
|
|
|
| |
|

CALL ORDER: 305
PROJECT NO.: RD-39-3(1005)
Boone, Platte Counties
Return to Lettings Index Page
|
CONTRACTOR |
TOTAL |
| DOBSON
BROTHERS CONST CO & AFFIL |
|
|
KNIFE RIVER MIDWEST LLC |
1,986,078 |
|
PAULSEN INC |
|
| SIMON
CONTRACTORS & SUBSID |
2,198,556 |
| U S
ASPHALT CO |
2,102,402 |
| WERNER
CONSTRUCTION INC |
1,966,512 |
| WESTERN
ENGINEERING CO INC |
|
| |
|
| |
|

CALL ORDER: 405
PROJECT NO.: RD-39-3(1006)
Nance County
Return to Lettings Index Page
|
CONTRACTOR |
TOTAL |
| DOBSON
BROTHERS CONST CO & AFFIL |
|
|
KNIFE RIVER MIDWEST LLC |
3,214,559 |
|
PAULSEN INC |
|
| SIMON
CONTRACTORS & SUBSID |
3,525,441 |
| U S
ASPHALT CO |
3,260,836 |
| WERNER
CONSTRUCTION INC |
3,052,013 |
| WESTERN
ENGINEERING CO INC |
|
| |
|
| |
|

CALL ORDER: 410
PROJECT NO.: STP-39-2(106)
Merrick, Platte, Nance Counties
Return to Lettings Index Page
|
CONTRACTOR |
TOTAL |
| DOBSON
BROTHERS CONST CO & AFFIL |
|
|
KNIFE RIVER MIDWEST LLC |
3,708,963 |
|
PAULSEN INC |
4,332,129 |
| SIMON
CONTRACTORS & SUBSID |
4,155,490 |
| U S
ASPHALT CO |
3,798,787 |
| WERNER
CONSTRUCTION INC |
3,646,335 |
| WESTERN
ENGINEERING CO INC |
4,037,939 |
| |
|
| |
|

CALL ORDER: 415
PROJECT NO.: RD-22-5(1016)
Nance County
Return to Lettings Index Page
|
CONTRACTOR |
TOTAL |
| DOBSON
BROTHERS CONST CO & AFFIL |
|
| KNIFE
RIVER MIDWEST LLC |
|
|
OMNI ENGINEERING INC & SUBSID |
978,405 |
|
PAULSEN INC |
|
|
SIMON CONTRACTORS & SUBSID |
|
| U S
ASPHALT CO |
|
| WERNER
CONSTRUCTION INC |
1,045,169 |
| WESTERN
ENGINEERING CO INC |
|
| |
|
| |
|

CALL ORDER: 500
PROJECT NO.: F-71-2(1006)
Kimball County
Return to Lettings Index Page
|
CONTRACTOR |
TOTAL |
| DOBSON
BROTHERS CONST CO & AFFIL |
11,585,146 |
|
INTERSTATE HIGHWAY CONST INC |
11,785,333 |
|
KNIFE RIVER MIDWEST LLC |
|
| UPPER
PLAINS CONTRACTING INC |
10,923,670 |
| WERNER
CONSTRUCTION INC |
12,790,382 |
| |
|
| |
|

CALL ORDER: 605
PROJECT NO.: IM-80-5(68)
Buffalo, Dawson Counties
Return to Lettings Index Page
|
CONTRACTOR |
TOTAL |
| DOBSON
BROTHERS CONST CO & AFFIL |
|
|
KNIFE RIVER MIDWEST LLC |
|
|
OMNI ENGINEERING INC & SUBSID |
8,641,961 |
|
PAULSEN INC |
7,943,530 |
| SIMON
CONTRACTORS & SUBSID |
8,847,251 |
| U S
ASPHALT CO |
|
| VONTZ
PAVING INC |
7,754,614 |
| WERNER
CONSTRUCTION INC |
7,581,023 |
| WESTERN
ENGINEERING CO INC |
|
| |
|

CALL ORDER: 610
PROJECT NO.: RD-83-2(1030)
Lincoln County
Return to Lettings Index Page
|
CONTRACTOR |
TOTAL |
| PAULSEN
INC |
2,170,141 |
|
SIMON CONTRACTORS & SUBSID |
2,263,408 |
|
U S ASPHALT CO |
2,272,739 |
| WERNER
CONSTRUCTION INC |
|
| WESTERN
ENGINEERING CO INC |
2,062,482 |
| |
|
| |
|
|
|